Reconstruction of Bardzka and Swieradowska Streets, Wrocław

Object of works: stabilization of the ground under the street and the tram lines along reconstructed streets; thickness of stabilization 20 cm or 25 cm 


Type of used material: subgrade stabilization mix 1,5-2,5 MPa, eco subgrade stabilization 1,5-2,5 MPa


Range of contract: around 15 thous. m3

Period of time for carrying out the project: 2009/2010


Supplier: Renevis Sp. z. o. o.